Grid Connection Guide
Understand grid interconnection processes, timelines, and requirements across European markets.
AI Grid Timeline Estimator
Get AI-powered estimates for your grid connection timeline
Country-Specific Grid Information
Browse detailed grid connection information for each European market.
France
Lead Time
13-22 months
Regional variations; southern regions have faster timelines
Connection Process
- 1.
Pre-study Request
1-2 months
- 2.
Full Study and Proposal
4-6 months
- 3.
Agreement Signature
2 months
3 documents required
Germany
Lead Time
18-36 months
North-South bottlenecks; offshore wind has dedicated capacity
Connection Process
- 1.
Informal Inquiry
1 month
- 2.
Formal Application
4-6 months
- 3.
Connection Offer
2-4 months
3 documents required
Spain
Lead Time
12-24 months
Significant queue in high-generation areas; prioritization for storage
Connection Process
- 1.
Pre-application Consultation
1 month
- 2.
Grid Access Request
3-6 months
- 3.
Connection Agreement
2-3 months
3 documents required
Note: Lead times are indicative and vary by project size, location, and grid capacity.