Grid Connection Queue Management Across Europe
Comparative analysis of how different countries handle grid connection applications and queue priorities
Published November 2, 2025
Full Article
Comprehensive analysis and insights on European clean energy markets
Grid connection queues vary significantly across Europe. Germany employs a first-come-first-served model with conditional milestones, while Spain recently reformed its system to prioritize projects with advanced development status. France uses a mixed approach with regional capacity allocation. Key insight: Storage projects are increasingly receiving priority treatment due to grid stabilization benefits. Best practice for developers: secure grid capacity early, maintain milestone compliance, and consider hybrid projects (solar + storage) for preferential treatment. Typical queue times range from 12 months (France, distribution level) to 36+ months (Germany, transmission level).